Fiber Update 10/22/23
9:52AM October 25, 2023
Newly Completed Locations
Construction
is complete, conduit is laid, and fiber is currently being activated in homes
in the following areas!
·
All of Moapa, including
the Warm Spring Area*
·
All of the Mills Street
area
·
Jensen Avenue in
Logandale
If you
live in these areas or know people who do, let them know they can now receive
fiber internet. This is the best internet technology that exists today– and
it’s available here! Check availability at your address at mvtel.com.
*With
the exception the Moapa Indian Reservation (update below on the Reservation.).
Current Projects
These
are areas where construction is active. Fiber has been pulled and the crew is
splicing it now (fancy term for joining two fiber optic cables together). Homes
in the following areas will be ready to be connected with fiber internet in
December of this year.
·
Cram Avenue
·
Whitmore Street
·
St. Joseph Street
·
Gubler Avenue
Lyman Street in Logandale: the digging is done, conduit is
laid, and fiber is expected to be pulled early next year.
Projects Beginning Soon
Moapa Tribal Indian Reservation has been added to the MVT
fiber build. Conduit has started to be laid. The Reservation Housing area which
will eventually serve approximately 72 homes is first on the list to be
completed. After that, MVT will be moving on to build out and connect the rest
of the Reservation.