It’s been a busy start to 2023, with areas going live with fiber, building underway in other areas, and new roads added to where we will bring fiber.

Newly Completed Locations

Warm Springs & Lytle Ranch

Construction is complete, conduit is laid, and fiber is currently being activated in homes in this area. If you live in this area or know people who do, let them know they can now receive fiber internet. This is the best internet technology we have today – and it’s available here!

Current Projects

Cram Avenue, Gubler Avenue and Lyman Street

In April of this year, we began laying conduit on Cram and Gubler Avenues. The following month we laid conduit on Lyman Street. These projects continue to be on track with the goal of connecting homes beginning summer 2024.

Projects that have started

Lawson Road in Moapa is on track for homes to be connected by late summer 2023. Construction is slightly ahead of schedule.

Wells Road in Logandale will have conduit laid late this summer. Fiber activation will be determined based on how construction goes in this area.
   

NEW AREA JUST ADDED! Jensen Avenue in Longandale has been added to our fiber build. Conduit has been laid and construction will be taking place throughout 2023-2024. 